Can RERA complete the pending project in the interest of allottees?

Builder absconding with booking money of allottees. Can rera complete the pending project in the interest of allottees? Builder has not started work in 7 years after initial mobilisation. Can landowner and few allottees jointly complete the project as builder absconding with booking money of allottees.

Can RERA complete the pending project in the interest of allottees? Builder absconding with booking money of allottees. Can rera complete the pending project in the interest of allottees? Builder has not started work in 7 years after initial mobilisation. Can landowner and few allottees jointly complete the project as builder absconding with booking money of allottees.

You should form an association of allottees and approach the RERA authority. Section 8 of the RERA Act empowers the authority to take over the pending project. 

The authority can approach and consult the government for construction of pending work and complete the project. But you have to file a complaint with the RERA authority. The time period fixed for the completion of the housing project must be expired on the date of filing of complaint.

As you said, the builder has absconded and is not traceable. In this situation no one will come forward to receive the notice. Hence, the proceeding before the RERA authority will proceed in the absence of the builder. 

In this situation the RERA may take over this project and approach the government to complete the project or permit the association of allottees to carry on the stalled project. 

Shivendra Pratap Singh

Shivendra Pratap Singh

Advocate

Advocate Shivendra, practicing law since 2005, specializes in criminal and matrimonial cases, extensive litigatin experience before the High Court, Sessions court & Family Court. He established kanoonirai.com in 2014 to provide dependable and pragmatic legal support. Over the years, he has successfully assisted thousands of clients, making the platform a trusted resource for criminal and matrimonial dispute resolution in India.

Related Matters

Lessor has refused to renew the lease even after receiving entire rent

A business owner in Gujarat faces a legal notice to vacate after their landlord refused to renew a lease, despite accepting rent in advance. Legal experts clarify that payment does not constitute an automatic renewal when written permission is required. While the lease terminates by efflux of time, the tenant may negotiate for sufficient relocation time.

My neighbor has constructed a 6 to 7-foot compound wall

This legal guidance explains the remedies available where a neighbour has raised a high compound wall obstructing light, air, access, or causing nuisance to adjoining property owners. It discusses municipal complaints, civil injunction suits, easement rights, and legal action that may be initiated against unauthorized construction.

My neighbor is constructing a house adjoining to my compound wall

This legal guidance explains the remedies available when a neighbour constructs a building adjoining the compound wall without maintaining the required setback. It discusses municipal complaints, easement rights relating to light and air, temporary injunctions, and civil remedies available to prevent unauthorized or nuisance-causing construction.

Suit dismissed for defect in parties

This legal guidance explains the consequences of dismissal of a civil suit due to non-joinder or misjoinder of necessary parties. It discusses the remedy of impleading proper parties, restoration or refiling of the suit, amendment of pleadings, and the legal principles governing defect in parties under the Civil Procedure Code.