Claim refund of money against the builder under RERA

I booked a flat in a development project situated in Lucknow, Uttar Pradesh. The builder said that the project would complete in July 2016. However, I booked the said flat in the year 2014, but it is still under construction. The builder refuses to return my hard-earned money. More importantly, I have paid the total amount in the year 2017. Now the worst scenario is the builder says that he has no money to complete this project and the LDA had restricted further construction. I want to file a complaint in RERA for return of the total amount. Whether the…

I booked a flat in a development project situated in Lucknow, Uttar Pradesh. The builder said that the project would complete in July 2016. However, I booked the said flat in the year 2014, but it is still under construction. The builder refuses to return my hard-earned money. More importantly, I have paid the total amount in the year 2017.

Now the worst scenario is the builder says that he has no money to complete this project and the LDA had restricted further construction. I want to file a complaint in RERA for return of the total amount. Whether the claim will be maintainable because I booked the flat before the commencement of RERA.

Your complaint is maintainable under Section 18 of The Real Estate (Regulation And Development) Act, 2016. However, you have booked the flat in the year 2014, but the project is still pending. The RERA came into force on 1st May 2017, and according to Section 3, all the ongoing projects come in its jurisdiction. Your builder did not get the completion certificate from the concerned authority. Therefore he cannot claim that his project is out of the RERA jurisdiction.

You may file a complaint before the RERA authority under section 18. This section empowers the buyer to claim a refund of the amount which he has paid to the builder and compensation for any other loss. This section also entitles the buyer to get simple interest upon the paid amount.

As far as the application of RERA provisions is concerned, it does not matter that you booked the flat in the year 2014 and paid the total amount in the year 2017. Section 3, 12141819, 71(1) and 79 of the Real Estate (Regulation And Development) Act, 2016, have retrospective effect. If a project is incomplete or does not get the completion certificate, then the RERA will applicable thereon.

Hence, you can file a complaint before the RERA authority under section 18 for the refund and compensation. If you do not want the refund of total amount and project is likely to complete shortly, then you are entitled to get simple interest on the amount. The interest will accrue from the date mentioned in the agreement for completion and transfer of possession of flat. Generally, the court orders lending rate of interest of SBI + 2 % simple interest on the investment. You are entitled to get interest from the date mentioned in the contract for giving possession of the flat.

Shivendra Pratap Singh

Shivendra Pratap Singh

Advocate

Advocate Shivendra, practicing law since 2005, specializes in criminal and matrimonial cases, extensive litigatin experience before the High Court, Sessions court & Family Court. He established kanoonirai.com in 2014 to provide dependable and pragmatic legal support. Over the years, he has successfully assisted thousands of clients, making the platform a trusted resource for criminal and matrimonial dispute resolution in India.

Related Matters

Lessor has refused to renew the lease even after receiving entire rent

A business owner in Gujarat faces a legal notice to vacate after their landlord refused to renew a lease, despite accepting rent in advance. Legal experts clarify that payment does not constitute an automatic renewal when written permission is required. While the lease terminates by efflux of time, the tenant may negotiate for sufficient relocation time.

My neighbor has constructed a 6 to 7-foot compound wall

This legal guidance explains the remedies available where a neighbour has raised a high compound wall obstructing light, air, access, or causing nuisance to adjoining property owners. It discusses municipal complaints, civil injunction suits, easement rights, and legal action that may be initiated against unauthorized construction.

My neighbor is constructing a house adjoining to my compound wall

This legal guidance explains the remedies available when a neighbour constructs a building adjoining the compound wall without maintaining the required setback. It discusses municipal complaints, easement rights relating to light and air, temporary injunctions, and civil remedies available to prevent unauthorized or nuisance-causing construction.

Suit dismissed for defect in parties

This legal guidance explains the consequences of dismissal of a civil suit due to non-joinder or misjoinder of necessary parties. It discusses the remedy of impleading proper parties, restoration or refiling of the suit, amendment of pleadings, and the legal principles governing defect in parties under the Civil Procedure Code.