Advocate has withdrawn the writ petition without consent of petitioner

I am working as headmaster of the school. My advocate has withdrawn the writ petition without consent of petitioner i.e. me. I joined the school in April 2013. Well Before my joining, in November 2012 ,an agreement had been made by the then headmaster for construction of a Kasturba building run under Bihar education project of sarv shiksha abhiyan.  But departmental engineers made no effort to get the work started, no lay-out was done by them. When I joined the school ,the departmental engineers and the officers began to put pressure on me to start the work. Lay-out was done…

I am working as headmaster of the school. My advocate has withdrawn the writ petition without consent of petitioner i.e. me. I joined the school in April 2013. Well Before my joining, in November 2012 ,an agreement had been made by the then headmaster for construction of a Kasturba building run under Bihar education project of sarv shiksha abhiyan. 

But departmental engineers made no effort to get the work started, no lay-out was done by them. When I joined the school ,the departmental engineers and the officers began to put pressure on me to start the work. Lay-out was done in june 2013. In the process, it was found that the available land was not sufficient enough to carry on construction work. 

The agreement was forced to be done without the land having been measured.It was a grave mistake on part of the engineers.In that situation, a new site adjacent to the previous site was searched. It was a vast and big ditch. The then executive engineer changed the design spread foundation was changed to pile foundation, plain structure was changed to RCC structure. 

Estimate was also changed.design and estimate was finalised on 17-08-2013. No fresh agreement was executed with me. Before it on 11-08-2013, Bihar government issued a new schedule of rates effective from 11-08-2013. But the estimate was prepared on the basis of rates prevailing in 2011. Between 2011 to 2013, the prices of materials and labour increased drastically. 

I had to suffer huge losses on account of high increases in prices of materials and labour. It was all due to the fault of engineers on account of which the work started very late.I was not a bit responsible. 

When measurement book was prepared,it was found that many works had not been incorporated despite the fact that they were in the design and the work was actually done. That again amounted to a huge loss. 

I preferred a writ petition in 2018 in Patna high court to direct the department to book the MB on the basis of 2013 schedule of rates which prevailed at the time of making the estimate and incorporate all the items which were left in measurement. 

But the sad fact is that after a lapse of four years in july 2022, my advocate all of sudden withdrew my case without my consent. When I asked the reason, he gave a quite vague explanation. He must have taken my consent. 

I am sadly surprised how he can withdraw my case without my consent. Please guide me what I can do in that situation. I can not leave out such a huge loss. I am determined to fight my case till the last remedy available.

The advocate cannot act in contrary to the interest of his client. If the client has not given his consent to withdraw his writ petition, the advocate cannot withdraw the writ petition on behalf of the petitioner. 

In this situation you should move a petition in the High Court for restore the writ petition and initiation of an inquiry against the advocate for his misconduct. This act i.e. withdrawal of writ petition without receiving consent or instruction of the petitioner, comes under the purview of misconduct as provided in the Advocates Act 1961.

Tags:

Shivendra Pratap Singh

Shivendra Pratap Singh

Advocate

Advocate Shivendra, practicing law since 2005, specializes in criminal and matrimonial cases, extensive litigatin experience before the High Court, Sessions court & Family Court. He established kanoonirai.com in 2014 to provide dependable and pragmatic legal support. Over the years, he has successfully assisted thousands of clients, making the platform a trusted resource for criminal and matrimonial dispute resolution in India.

Related Matters

Bank refused to obey the order of Lok Adalat

This legal guidance explains the remedies available when a bank fails to comply with a compromise order passed by the Lok Adalat despite receiving the settled amount. It discusses enforcement of the award, execution proceedings, contempt-related remedies, and the legal course available against arbitrary action of the bank.

Subsequent proceedings in arbitration matter

This legal guidance explains the legal consequences and subsequent proceedings arising after an arbitration award or order in an arbitration matter. It discusses enforcement of the award, challenge proceedings under Section 34 of the Arbitration and Conciliation Act, execution remedies, limitation periods, and the jurisdiction of courts in post-award disputes.

Civil court dismissed suit for want of jurisdiction

This legal guidance explains the remedies available when a civil court dismisses a suit on the ground of lack of jurisdiction. It discusses return of plaint under the Civil Procedure Code, refiling before the competent court, limitation protection, and the legal consequences arising from adjudication by a court lacking jurisdiction.

Admission in NRI quota can be changed afterwards

This legal guidance explains whether admission obtained under the NRI quota can subsequently be altered, cancelled, or converted to another category. It discusses eligibility conditions, consequences of misrepresentation, university regulations, refund issues, and the legal remedies available against arbitrary cancellation or change of admission status.

Claim related to motor accident in consumer forum

This article discusses whether a claim arising out of a motor accident can be pursued before a Consumer Forum in addition to or instead of proceedings before the Motor Accident Claims Tribunal (MACT). It examines the maintainability of such claims under consumer protection law, the liability of insurance companies, and the distinction between deficiency in service and statutory compensation under the Motor Vehicles Act.